Application outbox bridge compatibility¶
Status: Accepted architecture contract (Phase 6 Plan 07)
Requirement: BRDG-02 (compatibility slice)
Companion: 10-application-outbox-bridge.md, 09-client-protocol.md
Executable matrix: tests/conformance/bridge/compatibility_matrix.yaml
This document is the upgrade / downgrade / support-window contract for the
supported application-outbox bridge. It does not invent an independent bridge
versioning system; support is derived from the Phase 3.1 workhold Capabilities
advertisement and the Phase 6 intent schema major.
Ownership and sequence¶
- Probe workhold first. Before claiming any app-outbox row, the bridge fetches
GET /v1/capabilities(or an injected equivalent) and classifies the response withBridgeCompatibility. - Fail closed. Protocol-major mismatch, missing durable idempotent-enqueue
semantics, malformed bodies, unavailable discovery, and unknown required
capability state block polling. The runner makes zero app-store
claimcalls and zero workhold enqueues. - Then poll. Only a
SUPPORTEDresult permitsclaim→ enqueue → ack. - Re-check on resume. Every
poll_once(including after incompatibility or dependency recovery) re-runs the gate so a rolling workhold upgrade cannot silently resume delivery.
Operators observe incompatibility through Plan 06 health: queue_compatible=false
and ready=false after note_capability_mismatch, while pending intents remain
in the application outbox for rollback.
Distinct version axes¶
These identifiers are not interchangeable:
| Axis | Source | Current supported value |
|---|---|---|
| workhold protocol major | Capabilities.protocol_major (OpenAPI const) |
1 |
| workhold schema revision | Capabilities.schema_revision |
"0001" |
| Bridge package version | queue-client distribution version |
independently released |
| Intent schema major/minor | Persisted app-outbox envelope | major 1 (minor additive) |
Schema migration revision inside workhold storage, OpenAPI schema revision, bridge package version, and app intent schema version must remain distinct in logs, health notes, and support matrices.
Durable idempotent enqueue¶
The required capability for bridge delivery is durable idempotent enqueue. It is satisfied when:
Capabilities.enqueue_dedup_ttl_seconds > 0(authoritative Phase 3.1 signal), or- an explicit
durable_idempotent_enqueue=trueadditional property is present.
Absence, zero TTL, or an explicit false fails closed before any claim.
Additive and unknown handling¶
- Additive intent fields (
intent_extensions/ unknown keys under major 1) are ignored by tolerant bridges; the immutable enqueue request (target_queue,enqueue_request, identity) is unchanged. - Unknown extensible workhold error codes map to explicit
UNKNOWNhandling — never crashes and never treated as success. - Unknown additive fields on a valid capabilities document are tolerated when required semantics are present.
Supported vs rejected combinations¶
Declarative rows live in compatibility_matrix.yaml. Binary outcomes:
| Combination | Outcome |
|---|---|
| Intent 1.0 / 1.1-additive + workhold protocol 1 + durable enqueue present | supported |
| Intent major 2 + workhold protocol 1 | rejected (preserve pending) |
| Intent 1.x + workhold protocol 2 | rejected |
| Intent 1.x + workhold protocol 1 + durable enqueue missing/unknown | rejected |
| Discovery unavailable / malformed capabilities | rejected (fail closed) |
| Mixed current + older_tolerant replicas on intent 1.x | supported; same bridge:v1: key |
Rolling upgrade¶
Mixed old/new supported bridge replicas must:
- compute the same Plan 02
bridge:v1:idempotency key for the same identity; - create at most one workhold task identity under that key across ≥50 replay cycles;
- never rewrite persisted intent to force compatibility.
Downgrade and rollback¶
- Downgrade is rejected when persisted intents require unsupported semantics (for example intent schema major 2 on a major-1 bridge).
- Rollback guidance: leave pending rows untouched; restore a supported bridge /
workhold pair; resume polling only after capabilities classify as
SUPPORTED. - The bridge must never mutate durable intent to force a downgrade.
Support windows and sunset¶
Deprecation and sunset dates for workhold protocol majors and client distributions follow the Phase 3.1 / 3.9 support policy published with the OpenAPI contract and qualified client releases. This document does not invent separate sunset dates. When workhold publishes a protocol-major bump or removes durable enqueue semantics, bridges must fail closed before delivery and operators must roll forward or restore a supported pair.
Detection via Plan 06 health¶
| Signal | Meaning |
|---|---|
queue_compatible=false |
Compatibility gate failed (note_capability_mismatch) |
ready=false |
Bridge must not be treated as delivery-ready |
| Pending depth / oldest lag | Intents preserved in app DB — not data loss by itself |
Logs bridge compatibility gate blocked poll |